Reply To: 2.0 Operation 2017-12-21T14:49:08+00:00

HOME Forums Gateways EZSrve 2.0 Operation Reply To: 2.0 Operation

Post count: 1001

Can you provide the details of what the two Actions are actually doing? Are they turning On/Off X10 or Insteon devices? As much detail as you can provide and I’ll see if I can recreate here. Also did you consider using the multiple Events that are available from a single Action. Could be your two Actions are running together and they are creating a Insteon conflict on the powerline. For test purposes you can try putting say a 10 second delay on the Action Events of one of the Actions and see if creating a separation helps. Not suggesting you need a 10 second delay, just that should be enough to remove overlaps if one exists.